Important 3.45 GHz Clearinghouse Dates
March 6, 2023
3.45 GHz Search Committee releases RFP
March 6, 2023
May 2, 2023
Search Committee tentatively selects SRG for clearinghouse
May 2, 2023
July 3, 2023
SRG submits contracts to Search Committee
July 3, 2023
August 1, 2023
3.45 GHz Search Committee approves contracts
August 1, 2023
September 22, 2023
FCC Releases Public Notice of SRG's selection
September 22, 2023
November 2, 2023
FCC Releases Order Confirming SRG's selection
November 2, 2023
December 17, 2023
Clearinghouse review of costs and cost allocation notice due
45 days per FCC Order
December 17, 2023
January 16, 2024
License winner's payments or objections due
30 days per FCC Order
January 16, 2024
February 15, 2024
Payment to incumbents
30 days per SRG estimate
February 15, 2024
March 16, 2024
Any additional costs allocation notice
30 days per SRG estimate
March 16, 2024
April 1, 2024
Clearinghouse quarterly progress report to FCC due
Per FCC Order
April 1, 2024
April 1, 2024
Clearinghouse data security audit due
Per FCC Order
April 1, 2024
April 15, 2024
Additional cost allocation payment or objection due
30 days per FCC Order
April 15, 2024
May 5, 2024
Targeted clearinghouse shutdown (if no disputes)
SRG estimate
May 5, 2024
May 10, 2024
Clearinghouse audited report due to FCC
Per FCC Order
May 10, 2024
Summit Ridge will attempt to expedite the Clearinghouse and complete its duties faster than FCC requirements.