Four Years to Clear the Upper C-band. Less Than a Year to Decide Who Pays:
Announcing the Unofficial Guide for the Upper C-band Transition
Summit Ridge Group has published the Unofficial Guide for the Upper C-band Transition (104 pages, 246 footnotes), which lays out that calendar and the decisions inside it for the four groups the Order reaches: incumbent earth station operators, the three eligible satellite operators, airlines and aircraft owners facing radio altimeter retrofits, and the bidders who will pay for all of it.
The Commission adopted FCC 26-46 on July 22, 2026, released it two days later, and published it in the Federal Register on July 31, 2026, at 91 FR 48700. It reallocates 160 megahertz at 3.98–4.14 GHz for licensed terrestrial use, sets a 20-megahertz guard band, and directs incumbent Fixed Satellite Service operations into the remaining 40 megahertz at 4.16–4.2 GHz or out of the band. Most rules take effect September 29, 2026. Bidding is expected to close by July 2027 under the One Big Beautiful Bill Act. On the Commission’s own estimates, winning bidders will underwrite $4 to $5 billion in FSS clearing costs, $6.3 billion in clearing incentives, and $3.83 to $5.71 billion in altimeter rebates. That is roughly $14 to $17 billion before the clearinghouse’s own costs, and licensees bear the entire allowed amount, including anything above the estimate.
Five points from the paper:
1) This program brings far more claims than the last one – Verizon told the Commission that the Lower C-band clearinghouse had approved half of the more than 900 lump sum claims submitted as of the end of 2021, and 546 of the more than 2,000 space station operator claims as of the end of 2023. The Upper C-band adds a rebate program reaching roughly 38,000 rebate-eligible aircraft and about 50,000 altimeters. One claim per aircraft would put the aviation piece alone at more than ten times the claim volume of the entire Lower C-band program, and every group in this program shares one queue.
2) The lump sum election is a 60-day window on a six-month analysis – WTB must finalize the Cost Catalog within six months of release, or roughly January 24, 2027. That notice opens a single window for incumbent earth station operators to elect lump sum treatment, site by site, and the Commission has stated that no extensions are envisioned. The election cannot be reversed. Eligibility is frozen to the incumbent list of November 19, 2025, and no registration window is coming. An operator that begins its site-level analysis when the notice issues will be doing six months of work in 60 days.
3) The cost of claiming may exceed the two percent presumption – The Order carries over the 2% soft cost presumption from the Lower C-band. However, the Commission’s own Inspector General reported in March 2026 that project management fees in the Rip & Replace program came to 15% of hard costs on reimbursements actually paid through January 2026, and that figure excludes participants’ internal labor and financing costs. Holding comparable work to 2% asks this program to be administered roughly seven times more efficiently than the one the Inspector General examined. The presumption is not equally thin for everyone. Two percent of a satellite procurement is more money than that procurement’s paperwork needs, before financing costs. The exposure sits heaviest with claimants who have nothing large to average against, such as small filter claims, where the cost of filing can approach the value claimed.
4) Delayed payment is a material risk – SES reported an average of 323 days to reimbursement in the Lower C-band transition. The reality underneath that number is even worse. As of September 15, 2023, SES had submitted 1,311 claims, and the clearinghouse had processed 103, under 8% of the total. The 323 days was the average across those 103. Forty-two took more than a year, one was paid after 680 days, and 48 were approved only in part. The remaining 1,208 claims had no processing time to report because they had not been processed. The Order sets deadlines at nearly every step for the parties around the clearinghouse. It sets none for the clearinghouse’s own review.
5) A rebate is not a reimbursement – The FAA rule covers 43,562 aircraft carrying 62,810 radio altimeters. Rebates are fixed amounts by aircraft category, paid only after the retrofit is complete, and forfeited entirely for an aircraft that misses its deadline. The FAA prices an installed airplane unit at $80,000 to $120,000. Dividing the Commission’s estimates, the first-deadline group implies approximately $120,000 per altimeter, at the top of the FAA’s range. The second-deadline group implies about $75,000 at the point estimate and $109,000 at the cap. Where WTB sets each category within that spread decides whether an operator is funded or absorbing a quarter of its own retrofit. Draft rebate proposals are due no later than October 6, 2026.
Where we sit. Summit Ridge served as the Commission-confirmed 3.45 GHz Relocation Payment Clearinghouse, which closed on budget against the net cost initially projected to license winners and filed its audited final report in March 2025. We currently advise approximately 35% of Priority 1 recipients by dollar value in Rip & Replace, and we filed comments and ex parte letters in GN Docket No. 25-59. We may seek a role in administering the Upper C-band program, and readers should weigh our perspective accordingly. The rules described in the paper are also not yet fully in effect, and several implementation decisions, including the Cost Catalog, the lump sum amounts, and the rebate categories, remain open.
The Full 104 Page Guide (246 footnotes) is available for download, as well as a Four-Page Summary. The report consolidates all dates in the program into a single table and includes a claim-readiness checklist organized by claimant type, a comparison of the Lower and Upper C-band frameworks, and a glossary. WTB’s draft rebate proposals and the selection committee’s criteria should both surface within the next several weeks. We expect the two of them to say more about how this program will actually run than anything else on the schedule this year, and we will update the guide as they do. Do not hesitate to reach out to us with any questions.